Development Phases

Track the construction progress of the Skelton Gate estate, including completed and upcoming phases.

Work in progress — This data is a best-effort estimate based on planning applications and resident observations. Figures may be inaccurate or out of date. Do not rely on this page for legal or purchasing decisions.

Overall Progress

360 of 1509 homes complete

23% complete

Phase 1

In Progress

The first section of Skelton Gate, delivering a mix of 2, 3, and 4 bedroom homes on the north eastern part of the site.

Progress

360 of 438 homes · 82%

438 homes Started 2022-09 Expected 2026-12

Phase 2

Planned

The section of the site to the west, and south, of phase 1. Taylor Wimpey have submitted plans to build the whole of this phase, but it is unknown when work will start.

Progress

0 of 370 homes · 0%

370 homes Started 2027-01 Expected 2029-12

Phase 3

Planned

The final proposed section of the development. Land between the waste management site, and Skelton Lake. Details to be confirmed.

Progress

0 of 701 homes · 0%

701 homes