Development Phases
Track the construction progress of the Skelton Gate estate, including completed and upcoming phases.
Work in progress — This data is a best-effort estimate based on planning applications and resident observations. Figures may be inaccurate or out of date. Do not rely on this page for legal or purchasing decisions.
Overall Progress
360 of 1509 homes complete
23% complete
Phase 1
In ProgressThe first section of Skelton Gate, delivering a mix of 2, 3, and 4 bedroom homes on the north eastern part of the site.
Progress
360 of 438 homes · 82%
Phase 2
PlannedThe section of the site to the west, and south, of phase 1. Taylor Wimpey have submitted plans to build the whole of this phase, but it is unknown when work will start.
Progress
0 of 370 homes · 0%
Phase 3
PlannedThe final proposed section of the development. Land between the waste management site, and Skelton Lake. Details to be confirmed.
Progress
0 of 701 homes · 0%